Below are pictures of a state of the art storage facility built "Turn Key" by Ken Neans Construction. Even though I have coordinated many large projects up to $20 Million, and have 19 years of references available for clients of larger projects, we are now focusing on the excavation side of commercial and private projects. I would be happy to help you and your project with contacts of great subcontractors that I have used in the past. Please contact us for work that we can help you with or help you get in touch with other quality subcontractors.
Compacting sub grade survey stares show cut. Erosion control in place and
stabilized
entrance.
Almost
27,000 ft of piping and conduit were installed on this site. That is over
5 miles.
Remember
52-days from start - Underground in, sub grade done, 1st coarse of road base,
all piers poured including billboard and 1st building erected.
66-days from start. 10,000 sq ft. 3-Level mini - Storage slab is ready to pour. Conduit in foreground is in main electric room..
66-days
from start, Final coarse of road base complete on 4 acres. This is the way base
should look.
67-days from start and pouring 10,000 sq ft 3-level slab.
68-days
from start and ready to pave under the building. This is how base should
look. Note: Finish around manholes and piers.
68-days from start, Finished last edge of road base. Two courses for 12" deep over 4 acres.
70-days
from start and we're paving. 1st coarse Grade-3. Note Fence starting
in background.
70 days and paving, 2nd coarse of Grade-4 and fence in background.
72-days
from start and we're paving 1st coarse on back of project. Note finish on
road base.
Website pictures I wish I had taken sooner.
Another
website photo I wish I had taken sooner.
Still yet another website photo I should have taken sooner.